A job shows an 18% projected margin in month three. In month five it shows 16%. Month seven, 12%. It closes at 4%.

Every month the report was right by its own math. Every month the drop looked small enough to explain. Nobody lied. The report did what it was built to do with the numbers it was given, and the numbers were wrong in a way the report could not see.

That pattern has a name: profit fade. It is the most expensive thing a WIP report can hide, and most owners only see it in hindsight.

I have read WIP schedules from the operator's chair and from the boardroom. The report is the best single view of a project business you can get. It is also only as honest as its weakest input, and owners rarely ask which input that is.

/ SECTION 01How the WIP works, in one paragraph

Each job on the report gets a percent complete, usually cost to date divided by estimated total cost. Multiply that by the contract value and you get earned revenue. Compare earned revenue with what you have billed. Billed more than earned is an over billing, which is a liability: you owe the client that work. Billed less than earned is an under billing, which is an asset: the client owes you, in theory. Projected profit is contract value minus estimated total cost.

Look at what all of that rests on. Estimated total cost is cost to date plus the estimated cost to complete. Cost to date is a fact. Cost to complete is a forecast, and somebody on your team typed it in.

Cost to date is a fact. Cost to complete is a forecast.

/ SECTION 02Four ways the report lies

One: the stale cost to complete. The PM takes the original budget, subtracts the cost to date, and calls the remainder the cost to complete. That assumes the rest of the job goes exactly to plan, even if the first half did not. Estimated total cost comes out too low, so percent complete comes out too high, so you recognize revenue and profit too early. The truth arrives later as fade.

Two: the over billing that looks like cash. A front-loaded schedule of values bills early work at more than it cost. Cash lands in the bank and feels like profit. It is a liability: money for work you have not done yet. Spend it, and you fund the end of this job with the start of the next one.

Three: the under billing that hides a loss. Some under billing is timing: you did the work this month and bill it next month. Under billing that persists, or grows, often means cost you cannot bill: unapproved change work (note #07), or an overrun that the forecast has not admitted yet. Bankers and sureties know this, and they discount under billings for that reason.

Four: the missing committed cost. Cost to date usually counts invoices received. It does not count the purchase orders and subcontracts you have committed but not yet been billed for. A job can look on budget while a large commitment sits outside the report.

THE COMMON MISFIRE

The fade nobody saw

Margin drops a point or two a month. Each month the PM has a reasonable explanation, and the drop is too small to force a hard conversation. Nobody plots the trend. By the time the job is 80% complete there is nothing left to recover, and the fade lands on the year-end numbers, the bonding line and the next bank review at the same time.

/ SECTION 03Five lines to read every month

You do not need to audit the whole report. Read these five things, in this order.

  1. Projected margin against bid margin, per job, as a trend. Plot it month over month. A line that drifts down a point at a time is the fade, and you can see it months before it lands. Gains are worth asking about too: they often mean the cost to complete is stale in the other direction.
  2. Who updated the cost to complete, and when. If it has not changed in three months on a job that is moving, nobody is forecasting. Somebody is subtracting.
  3. Net over and under billings against cash. If your cash position depends on over billings, you are spending money you owe in future work.
  4. Under billings older than sixty days. List them by job. Each one needs a reason: billing lag, unapproved change, or overrun. Unknown is not a reason.
  5. Jobs past 50% complete with an unchanged margin. Possible, but rare. These are the jobs to ask about first.

/ SECTION 04The monthly WIP review

The report gets more honest when the people who own the forecast have to defend it out loud.

Hold a monthly review, about forty-five minutes. Each PM walks their jobs. For each job, the owner asks three questions:

Split ownership cleanly. The PM owns the forecast. Accounting owns the math and the cut-off. The owner owns the questions. When the PM knows the questions are coming, the cost to complete starts getting built from the work instead of from the budget.

This review is also where the earlier notes pay off. The turnover package (note #06) gives the PM a real plan to forecast against. The change log (note #07) tells you which under billings have a change order behind them and which do not.

/ SECTION 05What your banker and surety see

Your lender and your surety read the WIP closely, often more closely than the owner does.

They look at the fade history: do your jobs finish at the margin you projected, or below it? They look at under billings with suspicion and over billings as a debt you owe in future work. They look at working capital after both adjustments. And they look at whether the report changes in honest increments or in sudden write-downs at year end.

A firm whose WIP is accurate, with fade that shows up early and gets explained, earns trust. That trust shows up as bonding capacity and better credit terms. A firm whose WIP produces surprises pays for it, whether the surprise was good or bad.

/ SECTION 06Five questions to ask before the next report

  1. For each active job, who last updated the cost to complete, and how did they build it?
  2. Which jobs have faded more than two points since bid?
  3. How much of your cash is over billing?
  4. What is behind every under billing older than sixty days?
  5. Are committed costs on the report, or only invoices received?

If you cannot answer these from the report in front of you, the report is telling you a story, and you do not know how much of it is true.

This note closes a run on the life of a job's margin. Note #02 covered the leak before you bid. Note #06 covered the handoff after you win, note #07 the scope you build and never bill, and this one covers how all of it shows up, late, in the numbers you run the business on. Fix them in that order, and the WIP report starts telling you the truth while there is still time to act on it.

The frameworks are free. The work is the offer.